Drainage Layout Plan For Chack Shahzad

Date  : xxxxxxxx

Ref.    : xxxxxxxxxx
      
M/s. Your SUB –CONTRACTOR NAME
P. O. Box: xxxxx
Islamabad, Pakistan
Chack Shahzad
Tel: xxxxxxx Fax: xxxxxxxx

Attn.           :         Kamran Khan – Area Manager

Project        :         YOUR PROJECT NAME

Location     :         Chack Shahzad - Islamabad

Subject       :         Drainage Layout Plan For Chack Shahzad

Dear Sir,

With reference to your letter dated 23rd January, 2010 regarding the above mentioned subject, please find attached herewith the drawing Ref. No. 4607-4-400 for the Chack Shahzad drainage layout plan as per your request and please note that regarding water supply you are required to contact with CDA (Capital Development Authority) utility provider.

This is forwarded for your information and records.

Thanks,
For YOUR COMPANY NAME



Atif Ali Meer
Area Manager

Cc:   Main Office

        Engineering Dept.

Monday, 5 February 2018

Mechanical Excavation Permission for Main Gate

Date  :         xxxxxxx

Ref.    :         xxxxxxxxxxxxxxxxxxxx

M/s. YOUR SUB-CONTRACTOR NAME
P. O. Box: xxxxxxxxx, Lahore - Pakistan
Tel: xxxxxxxxxxx Fax: xxxxxxxxxxxxxxx

Attn.           :         Mr. Ghani Shah – Construction Manager

Project        :         YOUR PROJECT NAME

Location     :         Lahore - Pakistan

Subject       :         Mechanical Excavation Permission for Main Gate 

Dear Sir,

Reference is made to the above mentioned subject and further to your letter Ref. No. BYGC/17E/3096 dated 26th April, 2012 in which you are requesting Mechanical Excavation permit for the Access/Entrance works at M/s. Baghban Society, please be informed that as per your aforesaid Undertaking letter YOUR COMPANY NAME have no objection to proceed with your activity at site incompliance with M/s. Lahore Municipality site rules and regulations.

Please note that you are fully responsible for the aforementioned works in case of any damages that might occur to the existing underground services during your mechanical excavation works.

Moreover, all your excavation to be carried out under YOUR COMPANY NAME control and the mechanical excavations to be executed with high attention as per M/s. Lahore Municipality rules (Maximum 60 cm depth) and far from the close services, the rest to be executed manually especially beneath HV Cable area.

Prior commencement of works, please coordinate with YOUR COMPANY NAME Tel: ************ Hotline: 0800-******* in order monitor your site and provide any required assistance.

This is forwarded for your consideration and further action.

Thanks & best regards,
For YOUR COMPANY NAME



Malik Kamran Khan Awan
Engineering Manager
Encl: As Stated Above
Cc:   M/s. Lahore Municipality

         Head Office – Engineering Dept.                                                                                     

Existing Utilities & Sewer Connection at M/s. Beacon House

Date  :         XXXXXXXX

Ref.    :         XXXXXXXXX

M/s YOUR SUB-CONTRACTOR NAME
P. O. Box: XXXX, Islamabad - Pakistan
Tel:  XXXXXXXXXXXXXXXXXXXXXX
Fax:   XXXXXXXXXXXXXXXXXXXXXXX  

Attn.
:
Mr. Kamal Khan – Project Manager

Project
:
YOUR PROJECT NAME

Location
:
Islamabad - Pakistan

Subject
:

Dear Sir,

With reference to the above mentioned subject and to your request via letter ref: no. KH/J1402/AJT/BF/GD/B8/003 dated 25/09/2014, received on 28/09/2014; concerning the same, please find attached herewith hard & soft copy of drawings No. BB/14-118 & 245 depicting the existing sewer connection details allocated adjacent to the M/s. Beacon House in Islamabad along with existing utilities services as you have requested via aforesaid letter.

Kindly be informed that this drawing is NOT considered to allow you to proceed with any kind of works on site unless you contact YOUR COMPANY NAME for rules and proper procedures.

For further clarifications/details do not hesitate to contact with YOUR COMPAMNY NAME Team (Tel: ************** Fax: ************).

This is forwarded for your consideration and action.

Thanking you,
For YOUR COMPANY NAME





Eng. Ghani Shah
Area Manager

Encl: As mentioned above.

Cc:
§   Main Office
§   Engineering Dept.
§   Safety Officer






                                                

Saturday, 3 February 2018

Letter for Tenant Access/Entrance Approval For Rawal Lake

Date  :         DD/MM/YYYY

Ref.    :         XXXXXXXXXXXXXXXX

M/s. Sub Contractor Name
P.O. Box: xxxxx, Islamabad - Pakistan
Tel xxxxxxxxxx Fax: xxxxxxxxx 

Attn.           :         Area Manager

Project        :         YOUR PROJECT NAME

Location     :         Rawal Lake – Islamabad - Pakistan

Subject       :         Tenant Access/Entrance Approval
  For Rawal Lake - Islamabad
                  
Dear Sir,

Reference is made to the above mentioned subject and further to your letter Ref. No. (NIL) dated
22nd December, 2014 along with the signed Tenant Access Application Form, related documents and required drawings concerning the same, please be informed that YOUR COMPANY NAME have no objection to proceed with your activities at site as per the submitted drawings and comments as mentioned in Approval Form (i.e. The existing storm water inlet (IN/97/01/05) to be adjusted to the road level with heavy duty cover, Sewer Manhole close to Access line to be protected and avoided as per attached and Trash bin location to be provided) in compliance with M/s. CDA Islamabad Site rules and regulation.

We hereby attach the shop drawing Ref. No. CDA/TMA/Rawal/lakes/PLOTS-273 & 274 for the existing service protections and required future ducts at your entrance for your easy reference. 

Please note that you are fully responsible for the aforementioned works in case of any damages that might occur. All works will be under our supervision and all excavations to be executed manually.

Note: Commencement and completion of your Access Plot works must be within two (2) months from the date of issuance this approval and a set of As Built drawing (Hard + Soft copies) to be provided to YOUR COMPANY NAME upon completion and certification request for Clearance (NOC).

For any further details/clarifications and prior commencing your activity at site please coordinate with us (Tel: xxxxxxx Mobile: xxxxxxxx).

This is forwarded for your consideration and further action.

For YOUR COMPANY NAME


Basharat Khan
Construction Manager
Encl: As Stated Above
Cc: Head Office – Engineering Dept                                                                                       


Letter for Access Approval House No. 58A

Date  : XXXXXX

Ref.    : XXXXXXXX
      
M/s. YOUR CONTRACTOR NAME
Havelian Cantt

Attn.           :         Atif Ali Malang - CM

Project        :         your project name

Location     :         Havelian Cantt

Subject       :         Access Approval House No. 58A

Dear Sir,

Reference is made to the above mentioned subject and further to your letter dated 20th May, 2010 to M/s. POF and to the signed Tenant Access Approval Form, kindly be informed that we have no objection to proceed with your activities at site as per the submitted drawing and in compliance with the comments mentioned in the aforesaid Form which is stating that the existing two numbers of storm water inlet shall be changed/adjusted with the heavy duty flush inlet. We hereby attached the shop drawings for the existing service protections and required future ducts under your entrance for action.

Moreover, you are fully responsible for the aforementioned works in case of any damages     occurs, and all the works shall be under our supervision. In the mean time, you shall approach the other utility providers such as M/s. Sui Nothern Gas (O&M), Wapada, TMA and PTCL for further clearance.

For any further details/clarifications and before commencing your activity at site please coordinate with YOUR COMPANY NAME Team who are the site supervisors:

Supervisor Name:***********************
Telephone number: +092*****************

This is forwarded for your information and further action.

Thanks and best regards,
For YOUR COMPANY NAME


Hukam Dad Khan
Area Manager
Encl: As Stated Above

Cc:      Head Office

Letter for Drainage Layout Plan (House No. 57A)

Date  : XXXXX

Ref.    : XXXXXXXX
      
M/s. YOUR CONTRACTOR NAME
P. O. Box: XXXXX
Havelian - Pakistan
Tel: xxxxxx Fax: xxxxxxxx

Attn.           :         General Manger

Project        :         YOUR PROJECT NAME

Location     :         Havelian Cantt

Subject       :         Drainage Layout Plan (House No. 57A)

Dear Sir,

With reference to your letter Ref. No. 0611-09-91 received on 13th January, 2010 regarding the abovementioned subject, please find attached herewith the drawing Ref. No. 4607-4-400. 7A & C for House No. 57A drainage layout plan as per your request.

This is forwarded for your information and records.

Thanks,
For your company name



Eng. Kamal Khan jadoon
Area Manager

Cc:   Engineering Dept

       Head Office 

Friday, 2 February 2018

Write a Conservancy Violation (Housekeeping)

Date  : xxxxxx

Ref.    : xxxxxxxx
      
M/s. YOUR SUB-CONTRATOR NAME   
P. O. Box: XXXXX
Islamabad - Pakistan
Tel: XXXXXX Fax: XXXXXX

Attn.           :         General Manager

Project        :         YOUR PROJECT NAME

Location     :         YOUR PROJECT LOCATION

Subject       :         Conservancy Violation (Housekeeping)

Dear Sir,

With reference to the above mentioned subject and to our continuous site inspection, please find attached herewith photos shows that your contractors damaged the Interlocking tiles in front of your factory area (factory name) during the construction as they spilled concrete over the tiles.

Therefore, you are fully responsible for the aforementioned damages and you have to replace the interlocking tiles if it cannot be cleaned.  Please instruct your contractor to keep the city clean and to follow the site rules & regulations so that such violations will not be repeated.

For any further details please do not hesitate to contact undersigned.

This is forwarded for your information and further action.

Thanks and best regards,
For YOUR COMPANY NAME


Eng. Kamal Khan
Area Manager
Mobile: +92-303-xxxxxxx

Cc:   Head Office
       Safety Department