Thursday, 12 January 2023

The Contractor Response - Cost Proposal for Proposed Reinforcement Concrete Surround

Ref:        xxxxxx                                   Date: Thursday, 12th January, 2023

To:         M/s. xxxxxx

Attn.:       Engr.  Xxxxxx - Position

Contract No:   xxxxx

Project Name:  xxxxxxxx

Subject: The Contractor Response - Cost Proposal for Proposed Reinforcement Concrete Surround

 Dear Sir,

With reference to the above-mentioned subject and further to Engineer Letter Ref. (1), The Contractor hereby submits to the Engineer a written proposal for variation which is in the Contractor’s opinion, if will be adopted, will be the best cost to the Employer for the mentioned work, and will be a benefit to the Contract.

Accordingly, the Contractor has prepared this proposal in accordance with the requirements of Sub-Clause 13 [Variation and Adjustments] of the condition of the Contract.

The supporting particulars (i.e., Reinforced Concrete Class-A 30/20, Quotations, etc) for this proposal are attached herewith in order to enable the Engineer’s Personnel / Employer to issue his instruction at the earliest.

This is for your kind information, record and further necessary action.

Yours faithfully,

 For and on behalf of [your company name]

 

Engr. Name

Project Manager

Encl: As sated above

Cc:                    

 

Image For Sample Understanding

 

Tuesday, 27 August 2019

Shaheen Foundation PAF Staff Required

شاہین فاونڈیشن پی اے ایف
تحصیل ہیڈکواٹر ہسپتال ضلع ڈیرہ غازی خان میں مندرجہ ذیل آسامیاں خالی ہیں
ہیڈ نرس
چارج نرس
ای سی جی ٹیکنیشن
ڈینٹل ٹیکینیشن
آپریشن تھیٹر اسسٹنٹ
سٹور کیپر
ڈیٹا انٹری آپریٹر
ریڈیو گرافر
مڈوائف دائی
ڈرائیور
وارڈ سرونٹ
لیب اٹینڈنٹ
جونئیر کلرک
پلمبر
الیکٹریشن
سٹریچر ہئیرر
نائب قاصد
خاکروب
دھوبی
مالی
مصالچی
ویٹر
کک
لانگری
باورچی
Director Admin 
HR&N Welfare 
Shaheen Foundation, Sector 9/1 PAF Complex Islamabad
051-8354311
051-8354320

Position Vacant in FMH College of Medical & Dentistry Shadam Lahore

Position Vacant in FMH College of Medical & Dentistry Shadam Lahore
Fatima memorial College of Medical & Dentistry is a 470 bed, multi specifically Hospital Teaching institution. Fatima Memorial Hospital is an affiliate of Fatima Memorial Hospital College  of Medicine & Dentistry.

Professor ENT

Professor , Operative Dentistry

Associate Professor , EYE, ENT

Associate Professor - Surgery 

Associate Professor - Science of Dental Materials 

Assistant Professor - Anatomy 

Assistant  Professor - Medicine , Surgery, Accident & Emergence, Anesthesia, Family Medicine

Senior Registrar - Surgery, Medicine, ENT

CONTACT
Telephone : 042-111555600 Ext 424 / 311
hrd@fmsystem.org

Tuesday, 6 August 2019

Acceptance with Comments of Work Order


Our Ref. GEN/BHG/TG/003

Date: 14 November 2017
M/s. Tiger Environment
P.O. Box xxxx  Haripur – Pakistan
Tele: +Fax: +

Attn.                    :   Engr. Kamran Malik
Project
:
Hattar Industrial Area
Subject
:
  
Dear Sir,

We acknowledge with thanks the safe receipt of the above referenced Work Order, which we confirm acceptance subject to our conditions as listed below:
As discussed and agreed the Work Order execution until successful and timely completion shall be the full responsibility of M/s. AL Geemi & Partners Contracting Co. LLC.
M/s. Tiger Gulf shall not be held responsible of any breach of the Work Order caused by M/s. Al Geemi & Partners Contracting Co. L.L.C.
M/s. Tiger GULF shall not be responsible for the supervision of the execution of the Work Order (As detailed below) which will be carried out by M/s. Al Geemi & Partners Contracting Co. L.L.C;
·         Direct supervision of the physical work execution and ensure it meets all applicable requirements to the satisfaction of Hattar Management.
·         Ensure that all QA/QC procedures, along with submission of Material Submittals, Material Samples and application for approvals…etc implemented by M/s. Al Geemi & Partners Contracting Co. L.L.C, are meeting the applicable requirements of ADM specifications and to the satisfaction of Hattar Management.
·         Ensure that all HSE procedures implemented by M/s. Al Geemi & Partners Contracting Co. L.L.C, are meeting the applicable requirements of TMA and Hattar Management.


Contd. Page 2…

 
Page 2

·         Measurements of final quantities to be surveyed by Hattar Management, and agreed between all parties.
·         Preparation and submission of As Built Documents in the right format and number.
·         M/s. Tiger Gulf shall not be held responsible for any eventual claim whatsoever that might be raised by M/s. Al Geemi & Partners Contracting Co. L.L.C. in connection with the above referenced Work Order.
Particular Conditions:
5. Variations in quantities not to be limited to 20%. Measurement and approval of the final quantities to be made by M/s. Hattar Management P and M/s. Al Geemi. Payment to be based on the final quantities measured and approved by both parties, the payment will be issued directly to M/s. Al Geemi.
6. M/s. Tiger /Al Geemi reserves the right to include the VAT into the invoices in case the works goes beyond 2017.
10. M/s. Al Geemi shall be fully responsible for the preparation and submission of all Material Submittals and Material Samples for Hattar Management approval. Hattar Management to provide the approval to M/s. Al Geemi for the same within 5 days.
14. Liquidated damages not applicable.
15. Defects Liability and Warranty not applicable.

Hattar management is respectfully requested to issue the following letters:

-       A letter confirming ZONESCORP’s acceptance of the above conditions.

-       An official letter nominating M/s. Al Geemi & Partners Contracting Co. L.L.C as the subcontractor for the execution of the above mentioned works.

The above is for your consideration and acceptance.

Yours faithfully,

For and on behalf of Hattat Management



Ahmed George Malik
Area Manager

Saturday, 18 August 2018

Letter for Tenant Access Approval Noori Town


Date  :         02nd January, 2011

Ref.    :         xxxxxxxxxxx
      
M/s. xxxxxxxx
P. O. Box: xxxxxx
xxxxxx
Plot No. xxxxxx
Tel: xxxxxx Fax: xxxxxxxxx

Attn.           :         Mr. xxxxxxx – Construction Director  

Project        :         xxxxxxxxxxx

Location     :         xxxxxxxxxxx

Subject       :         Tenant Access Approval Noori Town

Dear Sir,

Reference is made to the above mentioned subject and further to your letter dated 28th December, 2010 along with proposed protection drawings; we have no objection to your proposal for the protection of existing collector line adjacent to your plot entrances (slab at a depth of 750mm from the surface level to avoid any caving of the soil below the road) and further follow the standard protection to the rest of the existing services incompliance with M/s. ZonesCorp Site rules and regulation.

Please note that you are fully responsible for the aforementioned works in case of any damages that might occur. All your works will be under our (xxxxx) supervision and all excavations to be executed manually.

For any further details/clarifications and before commencing your activity at site please coordinate with our representatives (xxxxxxxxxxxx).

This is forwarded for your information and further action.

Thanks and best regards,
For XXXXXXXXXX


xxxxxxxxx
Facility Manager

Encl: As Stated Above
Cc:  M/s. xxxxxxxxxxxxxxx
        
        

Letter for Conservancy Violation (Housekeeping)


Date  :         27th February, 2011

Ref.    :         xxxxxxx
      
M/s. xxxxxx 
P. O. Box: xxxxx
xxxxxxxx
Tel: xxxxxxxx Fax: xxxxxx

Attn.           :         Mr. xxxxxxxx

Project        :         xxxxxxxxxxxxx

Location     :         xxxxxxxxxxxx

Subject       :         Conservancy Violation (Housekeeping)

Dear Sir,

Reference is made to the above mentioned subject and to our (xxxx) continuous site inspections (Photos captured), we have spotted a conservancy violation on your plot by your suppliers/workers which is totally prohibited according to M/s. xxxxx site rules & regulations.
Therefore, under the authority provided to us by xxxxxxxxx; you are herby requested to take action to clean the area immediately and maintain Housekeeping for image of the city.
Please be instructed to your co-workers to stop such type of violations and follow the site rules & regulations hoping that such violations will not be repeated


This is forwarded for your consideration and immediate action.

Thanks & best regards,
For XXXXXXXXXXXXXXX


xxxxxxxx
Facility Manager
Encl: As Stated Above
Cc:           M/s. xxxxxxxxxxxxxx 

Letter for Telephone Cable Connection Works Babli


Date  :         02nd March, 2011

Ref.    :         ddddd
      
M/s. Xxxxxxxxx
xxxxxxx

Attn.           :         xxxxxxx - General Manager  

Project        :         xxxxxxxxx

Location     :         xxxxxxx

Subject       :         Telephone Cable Connection Works Babli

Dear Sir,

Reference is made to the above mentioned subject and further to your letter dated 02nd March, 2011 concerning the same, we have no objection to proceed with your activity (Telephone Cable Connection to the Plot No. Babli) incompliance with M/s. LWA rules & regulations.

Please note that you are fully responsible for the aforementioned works in case of any damages that might occur. All your works will be under our (xxxxx) supervision and all excavations to be executed manually.

For any further details/clarifications and prior commencing your activity at site please coordinate with our representatives (xxxxxxxx).

For any further details/clarifications please do not hesitate to contact with us.

This is forwarded for your consideration and action.

Thanks and best regards,
For xxxxxxxxxxxxxxxxxxxx

xxxxxxxxxxxxx
Facility Manager
Encl: As Stated Above
Cc:   M/s.Babli Town