Date : DD/MM/YYYY
Ref. : TUNNEL
– 045/ 18 /208
M/s. YOUR SUB-CONTRACTOR NAME
P. O. Box: XXXXX, Haripur - Pakistan
Tel:
xxxxxxxxxx Fax: xxxxxxxxxxxxx
Attn. : Atif
Khan – Site Manager
Project : YOUR
PROJECT NAME
Location
: Hattar
Industrial Area Haripur
Subject : Completion
Certificate for Access/Entrance
M/s. Volta
Works – Hattar haripur
Dear Sir,
Reference is made to the above
mentioned subject and further to your letter Ref. No.
dem/17/2015 dated 27th April 2015 received 27th April 2015 concerning the same, and
in accordance to YOUR COMPANY NAME site inspection to the Factory. Volta Works at
Hattar Free Zone Industrial city Haripur, AJC HFM hereby under the authority provided by The M/s. TMA do certify that your Access/Entrance to the Factory. Volta Works, and Service Corridor were executed and completed in compliance with M/s. TMA site rules and regulations (Photos attached).
dem/17/2015 dated 27th April 2015 received 27th April 2015 concerning the same, and
in accordance to YOUR COMPANY NAME site inspection to the Factory. Volta Works at
Hattar Free Zone Industrial city Haripur, AJC HFM hereby under the authority provided by The M/s. TMA do certify that your Access/Entrance to the Factory. Volta Works, and Service Corridor were executed and completed in compliance with M/s. TMA site rules and regulations (Photos attached).
Furthermore, the Completion
Certificate Application to your entire plot boundary and buildings must be
applied to M/s. TMA and the concerned authorities (Wapada, PTCL, SUI…etc) for
their further approval and Certification.
Please do not hesitate to contact
with YOUR COMPANY NAME Team Tel: XXXXXX
for further clarifications/details.
This is forwarded for your consideration
and further action.
Thanks and best regards,
For
YOUR COMPANY NAME
Eng. Rajnee Kanat
Field Manager
Encl:
As Stated Above
Cc:
M/s. TMA Haripur
Engineering Dept.
Head Office
No comments:
Post a Comment
thanks for your time, if you have any Question, write to us, we will contact you soon. Regards