Thursday, 22 March 2018

Permit/NOC for Soil Investigation Works (Kareem Town)


Date  :         04th September, 2012

Ref.    :         xxxxxxxx

M/s. xxxxxxxxx
P. O. Box: xxxxxxxxx
Tel.: xxxxxx, Fax: xxxxxxxxx

Attn.           :         Eng. Yousuf Khan – Director  

Project        :         xxxxxxxxxxxxxxx

Location     :         Kareem Town

Subject       :         Permit/NOC for Soil Investigation Works (Kareem Town)

Dear Sir,

Reference is made to the above mentioned subject and to your letter Ref. No. A|KTH.12.GL.315 dated 03rd September, 2012 along with required documents drawings concerning the same, please be informed that Your Company Name have no objection to proceed with your soil test/investigation works at site upon your submitted Undertaking Letter Ref. No. DSS.12.GL.315 dated 03rd September, 2012 incompliance with M/s. kareem Town rules and regulations and based on the following conditions.

  1. You are fully responsible for the aforesaid works in case of any damages might be happened/occurred to any of the existing services and to the M/s. kareem Town Assets. 
  2. Reinstate the site/service corridor to its original/previous status once you have finish site works.
  3. Your Company Name will visit the site once you have finished aforesaid works and to do the necessary inspections to ensure that the work is completed to the satisfaction of M/s. kareem Town and incompliance with site rule and regulations.

Prior site commencement of works, you are required to coordinate with Your Company Name Team (Tel: xxxx/Hotline: xxxxx) for further clarifications/details and assistance.

This is forwarded for your consideration and further action.

Thanks and best regards,
For Your Company Name


Kamal Khan
DC Client
Encl: As Stated Above
Cc:           M/s. Kareem Town
                TMA Haripur

No comments:

Post a Comment

thanks for your time, if you have any Question, write to us, we will contact you soon. Regards